Working out of scheme An fuller detail.

Financial responsi- bility of Consulting Engineer.

receipt of tenders, but before deciding on the

acceptance of any one of them. If the work is

to be done departmentally then it may be neces-

sary for the Consulting Engineer to examine his

previous estimates, taking into account any fluc-

tuations in prices, changes of design or other

causes tending to render them no longer applicable.

Should he sea reason to anticipate material ex-

cess over the sun sanctioned he should at once

bring the matter to the notice of the Crown

Agents that they may obtain the instructions of

the Secretary of State before proceeding.

8. Should the scheme described in the Con-

sulting Engineer's report not have been worked

out in full detail it will be desirable, if time

permits, to do this now, after further survays

if necessary.

Although it is possible under the departmental

system to begin the work without the full pre-

paration of plans specifications and quantities

which are indispensable for the proper letting of

a contract, yet the caraful preparation of pre-

liminaries affords the Government not only a reli-

able forecast of expenditure but also a means of

watching and checking the progress of the work

during construction. In this connection attan-

tion is called to the circular headed "Financial

Responsibility of Consulting Engineers" dated

March 1901 of which a copy is attached.